Anfield Energy gets Colorado review completion for JD-8 uranium mine permit
Colorado's Division of Reclamation, Mining and Safety finished its review of the permit application for Anfield's past-producing JD-8 uranium and vanadium mine, approving a 28.30-acre permit area and setting a US$620,000 reclamation financial warranty. The permit will be issued once the state verifies that warranty, and the Department of Energy has found the draft Environmental Assessment template acceptable, so federal review is moving forward. Restart is still conditional on permit issuance, DOE Mine Plan approval and operational readiness work, with a target of the end of the second quarter of 2027.
Key points
- DRMS decision letter dated September 29, 2026 approved a 28.30-acre permit and affected area and a US$620,000 reclamation financial warranty.
- The reclamation permit will be issued after the Division receives and verifies Highbury Resources' financial and performance warranty.
- On September 29, 2026, DOE found the draft Environmental Assessment template for the JD-8 Mine Plan acceptable, allowing NEPA review to proceed.
- Anfield targets restarting uranium and vanadium production at JD-8 by the end of the second quarter of 2027, subject to remaining approvals and readiness work.