Aris Mining reports Toroparu PFS: $2.8 billion after-tax NPV, 31.5% IRR at $3,600/oz gold
Aris Mining released the completed prefeasibility study for its Toroparu gold project in Guyana, reporting 5.9 Moz of proven and probable mineral reserves and an after-tax NPV at 5% of $2.8 billion at a $3,600/oz gold price. The project has an initial funding requirement of $1,005 million, and the company still needs the large-scale mining licence and other approvals before targeting a construction decision in early 2027. For shareholders, the study sets out a larger, long-life project, but its timing depends on regulatory approval and financing.
Key points
- Proven and probable gold reserves of 5.9 Moz at $1,950/oz; 5.6 Moz planned production over 29 years.
- After-tax NPV at 5% of $2.8 billion and IRR of 31.5% at $3,600/oz gold; payback of 2.2 years.
- Initial funding requirement of $1,005 million, partly offset by $138 million of Wheaton funding.
- 32-month construction schedule; construction decision targeted for early 2027, subject to approvals.
The filing
Written by AI on Nov 23, 2026, 1:15 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on November 12, 2026.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.