B2Gold Goose Mine on track for 170,000-200,000 oz in 2026; new high-grade drill results
B2Gold said its Goose Mine is on track to meet 2026 gold production guidance of 170,000 to 200,000 ounces after a new mobile crushing plant reached about 3,000 tonnes per day, following an April fire at the fixed crushing plant. The company also reported 2026 exploration drill results from the Back River Gold District in Nunavut, including a new zone called Tattuk. Guidance was maintained rather than changed, and the fixed plant is not expected to reach 3,200 tonnes per day until October 2026.
Key points
- Mobile crushing plant has exceeded an average of 3,000 tonnes per day since mid-August 2026, at a capital cost of about $16 million.
- Fixed crushing plant Phase 1 upgrades, estimated at $11 million, are expected to be commissioned in mid-October 2026, with throughput of 3,200 tonnes per day expected from October.
- Annual 2026 Goose Mine production guidance is unchanged at 170,000 to 200,000 ounces of gold, with fourth quarter expected to be the strongest quarter.
- Drill hole 26GSE750Z2 returned 10.94 g/t gold over 9.95 m from 1,195.90 m, marking the new Tattuk discovery; drill results are as of August 31, 2026.