Every material Form 8-K Contango Silver & Gold Inc. has filed with the SEC since September 22, 2026, read and summarized by AI: what happened, the key figures, whether it reads positive or negative for shareholders, and how big a deal it is (impact 1-5). Newest first; each brief links to its own page and to the filing on SEC.gov.
Contango Silver & Gold reported an update on its 2026 field season in Alaska and British Columbia, in a press release furnished under Item 7.01. Kitsault drilling totaled 56,492 meters against 40,000 meters originally planned, and Johnson Tract infrastructure was completed ahead of schedule and under budget. The company also said Manh Choh unit cash costs for the third quarter are expected to be similar to second-quarter 2026 levels, and it is guiding to the lower end of its 2026 production guidance.
Kitsault: 56,492 meters drilled across 152 holes, versus 40,000 meters planned; drilling completed October 15, 2026, with assays pending over the next 2-3 months
Johnson Tract: 2.6-mile access road and portal lay down area completed ahead of schedule and under budget; a camp pad originally planned for 2027 was also completed
Manh Choh: third processing campaign ended September 24, 2026, earlier than planned due to rain and higher reagent use; Q3 unit cash costs expected similar to Q2-2026
Third-quarter 2026 financial results are scheduled for release in mid-November 2026
Contango Silver & Gold reported additional gold assay results from its 2026 surface drilling at the Lucky Shot Project in Alaska, including 140.23 g/t gold over 0.63 meters in hole LSS26018. The release also updated underground development, which is 450 of a planned 830 meters complete, and KM vein drilling, which began September 16, 2026. The filing says the Lucky Shot work is exploratory, no mineral reserves have been declared, and the results do not demonstrate economic viability, so the update does not change the company's financial results.
LSS26018 intersected 140.23 g/t gold over 0.63 meters and 9.97 g/t gold over 4.57 meters, including 86.98 g/t gold over 0.39 meters
The 2026 surface drilling program ended August 31, 2026, with about 5,800 meters drilled in 27 holes versus a planned program of about 6,000 meters
Underground exploration development has advanced 450 of 830 planned meters, about 54%, with completion expected in the middle of the fourth quarter of 2026
KM vein underground drilling began September 16, 2026, with 10 of 17 planned holes completed and assay results expected in the fourth quarter of 2026
Contango Silver & Gold said on September 22, 2026 that it completed a Technical Report Summary on its Kitsault Valley Project, with an effective date of September 11, 2026, under SEC mining property disclosure rules. The company also made a new corporate presentation available the same day. The filing states that no measured mineral resources or mineral reserves are reported for the project, and that the estimate supports continued evaluation rather than a mine development decision.
Technical Report Summary dated September 21, 2026, with a mineral resource effective date of September 11, 2026
No measured mineral resources or mineral reserves are reported for the Kitsault Valley Project
The company states the estimate does not establish a mine development decision
Qualified Person Dave Larimer, CPG, Vice President Exploration, signed the report on September 18, 2026
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.
Only material 8-Ks get a brief: results, deals, executive changes, restructuring, impairments, delisting notices, restatements, cybersecurity incidents and other disclosed events. Routine filings (vote results, exhibits only) are skipped. Every Contango Silver & Gold Inc. filing is on SEC EDGAR ↗. 8-K briefs of other companies →