Denison Mines moves Phoenix uranium mine into full-scale construction
Denison Mines announced that site preparation at its Phoenix ISR uranium mine in Saskatchewan has finished and full-scale construction has started, including the start of perimeter freeze wall installation for Phase 1. The company said the milestone supports its first-year construction plan, but the release contains no financial results, cost figures or updated timeline beyond the August start of key concrete work.
Key points
- Full-scale construction began at Phoenix in July 2026, after site preparation that started in March 2026.
- Temporary camp capacity was raised to nearly 400 people to support a ramp-up in the on-site workforce.
- Schedule-critical concrete work for the substation and main process plant foundations is expected to start in August.
- Denison says about 20% of overall site civil work is estimated complete.
The filing