Electra Battery Materials says cobalt refinery remains on $73 million budget
Electra Battery Materials said its cobalt sulfate refinery in Ontario remains within its $73 million budget, with the site workforce growing to 130 from about 60 in August. The company flagged schedule pressure in the solvent extraction area's fiberglass piping work, but said any adjustment is expected to be modest.
Key points
- Project budget: $73 million, which the company says the project continues to track within
- Site workforce: 130 people, up from approximately 60 at the August update
- Schedule: pressure in FRP process piping fabrication and installation; company is evaluating measures to accelerate, with any adjustment expected to be modest
- Tailings storage facility Phase II civil works approximately 40% complete