Ellomay receives grid access permit for 22.2 MW / 100.3 MWh battery storage in Spain
Ellomay said its Spanish subsidiary Ellomay Solar S.L. received a grid access and connection permit for a battery storage facility of up to 22.2 MW / 100.3 MWh (4.5-hour) at its solar site in Talaván, Spain. The company said the separate charging permit should improve the project's flexibility and profitability, and it called battery storage a core growth engine. The filing gives no cost, financing or revenue figures.
Key points
- Permit covers a battery storage facility of up to 22.2 MW / 100.3 MWh (4.5-hour), to be built on land already leased to Ellomay Solar
- The facility also received a permit to charge 22.2 MW from the grid
- Construction is expected to start in early 2027 and finish in the fourth quarter of 2027
The filing
Written by AI on Nov 23, 2026, 1:36 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on September 29, 2026.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.