EnerSys to close Tijuana, Mexico battery plant with pre-tax charge of about $37 million
EnerSys said it will close its lead-acid battery manufacturing facility in Tijuana, Mexico, and move most production to its Springfield, Missouri plant. The company expects a pre-tax charge of about $37 million, of which $14 million is non-cash, and an estimated annual pre-tax benefit of about $20 million starting in fiscal 2028. Shareholders face the near-term charge in exchange for projected cost savings, and the restructuring is expected to be substantially complete by December 2027.
Key points
- Pre-tax charge of about $37 million: $14 million non-cash, mainly equipment write-offs, and about $23 million in cash charges
- Estimated annual pre-tax benefit of about $20 million, beginning in fiscal year 2028
- Reduction of about 474 employees upon completion; the company also plans to sell the Tijuana land and buildings and possibly plant and equipment
- Restructuring expected to be substantially complete by December 2027, with most charges incurred by the second half of fiscal year 2027