Endeavour Silver completes Pitarrilla feasibility study with $736 million after-tax NPV
Endeavour Silver published a feasibility study for its Pitarrilla project in Durango State, Mexico, projecting an after-tax NPV of $736 million at a 5% discount rate and an initial capital cost of $585 million. The company says the project would be a long-life growth asset, with an 18-year mine life and planned average annual production of 7.5 million ounces of silver equivalent. The study is a milestone toward a development decision, but key tailings facility permits remain outstanding.
Key points
- After-tax NPV (5%) of $736 million and after-tax IRR of 16.37%, based on a $50.00 per ounce silver price assumption
- Initial capital of $585 million over a 30-month construction period, plus $119 million of sustaining capital over the mine life
- Planned average annual production of about 7.5 million ounces silver equivalent over an 18-year mine life; break-even silver price below $30 per ounce
- Tailings Storage Facility permit and other approvals still outstanding; technical report to be filed on SEDAR+ within 45 days; management call on November 20, 2026