i-80 Gold Granite Creek Study Shows $118 Million After-Tax NPV at $2,750 Gold
i-80 Gold filed a Pre-Feasibility Study for its Granite Creek Underground Project, dated September 21, 2026, with an effective date of March 31, 2026. The study reports an after-tax NPV (5%) of $118 million and a mine life of 8.5 years at a $2,750 per ounce gold price, and it supersedes the March 2025 Preliminary Economic Assessment.
Key points
- After-tax NPV (5%) of $118 million and pre-tax NPV of $138 million at a $2,750 per ounce gold price
- Proven and probable mineral reserves of 2,198 thousand tonnes at 7.87 g/t gold, containing 556.5 thousand ounces
- Life-of-mine total cash costs of $2,076 per ounce and all-in sustaining costs of $2,273 per ounce, with total capital and closure costs of $144.9 million
- Study prepared by third-party firms including SRK Consulting (U.S.), Inc. and Hatch Associates Consultants, Inc., with an effective date of March 31, 2026