Ionic Digital's Ward County 466 MW load classified provisionally as Base Load by ERCOT
Ionic Digital said the Texas grid operator ERCOT has provisionally classified the remaining 466 megawatt energization request for its Ward County campus as Base Load in its Batch Zero process. The classification is provisional and remains subject to ERCOT verification, audit and final determination under PUCT oversight, and the company continues to target energization of the final tranche by the end of 2027.
Key points
- ERCOT provisionally classified the remaining 466 MW request as Base Load in the Batch Zero process.
- Full energization would bring the Ward County campus to an aggregate demand of 700 MW.
- The company continues to target energization of the final tranche by the end of 2027.
- The classification remains provisional, subject to ERCOT's ongoing verification, audit and final classification, with PUCT oversight.
The filing
Written by AI on Nov 9, 2026, 11:46 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on September 10, 2026.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.