NVIDIA backs up to $105 billion in lease guaranties for SB Energy Ohio AI campus
NVIDIA entered multiple residual value guaranties with SB Energy covering leases for about 4.25 gigawatts of IT load at the PORTS-Pike campus in Pike County, Ohio, with OpenAI as tenant. NVIDIA's aggregate payment obligation for its initial commitment is capped at $105 billion, and it can provide additional credit support for about 3.8 gigawatts more at its discretion. The commitment is large and long-dated, and NVIDIA would pay if OpenAI defaults on a lease, though OpenAI has agreed to reimburse amounts NVIDIA pays.
Key points
- Guaranties cover leases for about 4.25 gigawatts of IT load; NVIDIA's initial payment obligation is capped at $105 billion.
- Payments are subject to conditions, including ready-for-service conditions under the leases, expected beginning in 2028.
- A payment is triggered if OpenAI becomes insolvent or fails to make lease payments; OpenAI must reimburse NVIDIA for amounts paid.
- NVIDIA will invest $1.5 billion in SB Energy, according to the attached press release.