Osisko Gold says Cariboo project 28% complete, but cuts underground development rate target
Osisko Gold reported that its Cariboo Gold Project is about 28% complete and remains on schedule for first gold pour in Q1 2029 and commercial production in H2 2029. The company also lowered its year-end 2026 underground development target to about 360 metres per month from 500 metres per month, citing slower excavation and rock and cold-weather conditions, which could affect the mine's ramp-up.
Key points
- Approximately C$355 million incurred through September 30, 2026; estimated remaining cost to complete construction is about C$907 million
- Underground development target by year-end 2026 cut to about 360 metres per month, from 500 metres per month previously
- Detailed engineering about 42% complete; over 50% of procurement packages awarded, with about C$360 million committed project-to-date
- Permitting: licence of occupation for the transmission line expected in Q4 2026