Sunshine Silver advances Sunshine Mine readiness; feasibility study due Q2 2027
Sunshine Silver Mining & Refining reported progress on underground development, infrastructure upgrades and site preparation at the Sunshine Mine in Idaho, and reaffirmed a feasibility study target of the second quarter of 2027 and a planned return to production in late 2028. The update contains no financial results, revenue, earnings or changes to guidance, so it mainly confirms the existing timeline for shareholders.
Key points
- About 1,200 meters of underground development were completed in the first half of 2026, with about 700 of the planned 1,300 second-half meters done as of September 30, 2026.
- Approximately 47,600 meters of the 50,000-meter infill drilling program were completed as of September 30, 2026.
- The legacy mill demolition is expected to be completed by year-end 2026, and the feasibility study remains targeted for the second quarter of 2027.
- The company plans a return to production in late 2028 and has designed initial processing of up to about 1,000 tons per day, with capacity for up to about 2,000 tons per day.