TC Energy outlines next NGTL growth phase, proposes Alberta Growth Connector pipeline
TC Energy said it plans the next phase of growth on its NGTL gas system, including the proposed Alberta Growth Connector, an approximately 370-kilometre pipeline linking Western Canadian gas supply to Alberta's oil sands region. The company forecasts system demand will rise about 25% over 2026-2031, from 14.4 Bcf/d to about 18 Bcf/d, with more than 60% of the increase expected from oil sands, power generation and data centres. The project remains subject to commercial support, regulatory approvals and TC Energy's sanctioning process, so shareholders face no firm investment decision yet.
Key points
- Forecast total NGTL demand rises from 14.4 Bcf/d in 2026 to about 18 Bcf/d in 2031, about 1.5 Bcf/d above the 2025 plan outlook
- Proposed Alberta Growth Connector would initially add about 1 Bcf/d of capacity and is a 370-kilometre, 48-inch pipeline
- Additional service offerings could launch as early as January 2027 and could exceed 1.3 Bcf/d of new delivery service between 2030 and 2032
- About $1.2 billion of sanctioned NGTL expansion projects are in progress; the 2026 NGTL System Annual Plan is expected to be filed by year end
The filing
Written by AI on Nov 23, 2026, 1:15 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on November 16, 2026.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.