TRX Gold expands Buckreef plant scope; capital costs now $45-$50 million
TRX Gold said additional test work showed recovery rates of 89% to 92%, above the 88% assumed in the May 2025 PEA, and it has specified a larger 3,500+ tpd SAG/Ball mill plant for its Buckreef Gold Project. The company now expects total plant expansion and upgrade capital costs of $45 to $50 million, about $10 to $15 million above the initial PEA estimates, and expects average annual gold production above the 62,000 ounces in the PEA. The changes are still in planning, so shareholders face higher expected spending alongside a larger expected production profile.
Key points
- Recovery rates of 89% to 92% from additional test work, versus 88% assumed in the PEA
- New SAG/Ball mill plant of 3,500+ tpd, versus 3,000 tpd in the PEA; SAG mill orders expected in Q3 2026 with estimated completion in Q2 2027
- Capital costs now $45 to $50 million, approximately $10 to $15 million above initial PEA estimates
- Existing 2,000 tpd plant upgrades expected to be completed by Q4 2026; updated PEA by P&E Mining Consultants expected in Q4 2026
The filing
Written by AI on Nov 23, 2026, 2:07 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on April 8, 2026.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.