Vizsla Silver delays Panuco first silver production to H2 2028 from H2 2027
Vizsla Silver moved its target for first silver production at its Panuco project in Mexico back one year, to the second half of 2028 from the second half of 2027, citing permitting, site readiness and construction timing. The company said it has not updated the November 2025 Feasibility Study economics for the revised schedule, potential cost escalation or financing costs, and it has not made a production decision.
Key points
- First silver production target revised to H2 2028 from H2 2027
- About 50% of engineering and about 85% of process plant equipment ordered, per the filing
- Initial contribution of US$5 million committed to the Vizsla Foundation
- No production decision; Feasibility Study after-tax NPV (5%) of US$1.8 billion not updated for the new timeline
The filing
Written by AI on Nov 23, 2026, 1:15 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on November 19, 2026.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.