Worthington Steel subsidiary gets CAD $57.5 million BDC loan for Burlington plant
Tempel Canada Company, a Worthington Steel subsidiary, signed a letter of offer on March 25, 2025 with Business Development Bank of Canada for a loan of up to CAD $57.5 million to build a new manufacturing facility in Burlington, Ontario. Worthington Steel will guarantee part of the loan and provide cost overrun and completion guarantees, which adds financial exposure for the parent company.
Key points
- BDC committed up to CAD $57.5 million, subject to customary closing conditions; the loan matures June 1, 2051
- Worthington Steel guarantees Tempel Canada's loan obligations, limited to 20% of the loan amount on the date of any demand, with release possible once the balance reaches CAD $40 million
- Loan is secured by a mortgage on the Burlington property and a lien on certain equipment; draw period lapses March 21, 2026 unless extended
- Tempel Canada must maintain a Total Debt to Tangible Equity Ratio of 1.0 to 1.0 and a Fixed Charge Coverage Ratio of 1.15 to 1.0, tested annually