Every material Form 8-K WESTWATER RESOURCES, INC. has filed with the SEC since April 01, 2026, read and summarized by AI: what happened, the key figures, whether it reads positive or negative for shareholders, and how big a deal it is (impact 1-5). Newest first; each brief links to its own page and to the filing on SEC.gov.
Westwater Resources Executive Chairman Terence Cryan presented at the H.C. Wainwright 28th Annual Global Investment Conference on September 14, 2026, and the company furnished the investor presentation as Exhibit 99.1 to an 8-K. The presentation provides updates on the company's business plan, and the filing includes no new financial results.
Presentation given September 14, 2026 at 2:00 p.m. ET; posted to the company website the same day
Kellyton Graphite Plant Phase 1 development capital of $245 million, with approximately $130 million spent as of June 30, 2026
$25 million EXIM direct loan approved for Kellyton, announced August 7, 2026
Cash on hand of $38.2 million as of June 30, 2026; Coosa permitting presentation projects production expected late 2028 / early 2029
Westwater Resources said its Executive Chairman Terence Cryan and CFO Steven Cates will present at the Moneyshow Investor Conference on April 9 and April 10, 2026, using an investor presentation furnished as Exhibit 99.1. The presentation, also posted to the company website, provides updates on the company's business plan, including its Kellyton Graphite Plant and Coosa Graphite Deposit. The filing contains no new financial results.
Presentations scheduled for April 9, 2026 at 11:00 a.m. ET and April 10, 2026 at 10:45 a.m. ET
Investor presentation dated April 9, 2026, furnished as Exhibit 99.1 and posted to the company website on April 9, 2026
Presentation cites Kellyton Phase 1 development capital of $245 million, with about $130 million spent as of December 31, 2025
Presentation cites cash on hand of $48.6 million as of December 31, 2025
Westwater Resources disclosed that SK On Co., Ltd. terminated its Products Procurement Agreement, which covered purchases of CSPG natural graphite anode products, effective immediately after notice was received on March 31, 2026. The agreement covered a portion of the planned Phase I production capacity at the Kellyton Graphite Plant, so shareholders lose a named customer commitment for that capacity, though SK On has indicated it may consider future agreements on updated terms.
SK On notified Westwater on March 31, 2026 that it was terminating the Procurement Agreement effective immediately.
The agreement, signed February 5, 2024, covered a portion of planned Phase I capacity at the Kellyton Graphite Plant.
SK On has indicated a willingness to consider future agreements, subject to updated terms and conditions.
Westwater expects initial battery-grade graphite production within approximately 12 months of securing the remaining project financing.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.
Only material 8-Ks get a brief: results, deals, executive changes, restructuring, impairments, delisting notices, restatements, cybersecurity incidents and other disclosed events. Routine filings (vote results, exhibits only) are skipped. Every WESTWATER RESOURCES, INC. filing is on SEC EDGAR ↗. 8-K briefs of other companies →