DTE Energy discloses supply and energy storage deals for 1.4 GW Oracle data center in Michigan
DTE Electric, a DTE Energy subsidiary, entered a Primary Supply Agreement and an Energy Storage Agreement with Green Chile Ventures LLC, a wholly owned subsidiary of Oracle Corporation, to serve a future data center in southeast Michigan. The filing does not give financial values for either agreement, and the board approved them on October 28, 2025.
Key points
- Primary Supply Agreement: approximately 1.4 gigawatts of electric service, term through February 2045, full delivery expected in December 2027
- Energy Storage Agreement: DTE Electric to build and operate approximately 1.4 gigawatts of storage at Customer's cost, with each facility operated for 15 years
- Customer's parent provides credit support to DTE Electric for both agreements
- Full texts to be filed with the 2025 Form 10-K
The filing
Written by AI on Nov 8, 2026, 1:10 AM ET, from this filing only. Written later: this filing was briefed after the fact, when past filings were added to the site, so the brief may be read with hindsight; the filing itself is the record of what was known on October 31, 2025.
Briefs are written by AI from the filing text and can contain mistakes — open the filing before acting on anything. Impact (1-5) and tone are the AI's reading of the filing for shareholders, not a price forecast. Not investment advice.