TMCR's Mesabi iron ore project fires first production blast on July 10, 2026
TMCR said its royalty asset, the Mesabi Metallics iron ore project in Nashwauk, Minnesota, completed its first production blast on July 10, 2026, opening the first ramp into the pit for haul trucks. The company expects to begin receiving royalty revenue as production starts and ramps up, but the filing reports no revenue yet and gives only projected cash flow figures.
Key points
- First production blast on July 10, 2026, using a 66-hole pattern to fracture approximately 211,000 tons of ore
- Mesabi Metallics targets commissioning in H2 2026; the company says the blast keeps the project on schedule for first pellet production
- TMCR's 1.0% royalty has anticipated annual royalty cash flow potential of approximately $11 million per annum at 7.28 Mtpa over 23 years, with a near-term pathway to $13 million per annum at 8.5 Mtpa
- Mesabi Metallics operating data is provided by the operator and has not been independently verified by TMCR