TMCR Reports Mesabi Project 95.5% Complete, Line 1 Commissioning Targeted for Summer 2026
The Metals Royalty Company said the Mesabi Metallics iron ore project in Nashwauk, Minnesota, was 95.5% complete as of May 31, 2026, following an executive site visit by CEO Brian Paes-Braga. The company said it believes the project remains on track for commissioning of Line 1 in July/August 2026, but it does not operate or control the project and has not independently verified the third-party information it relies on.
Key points
- Overall project completion was 95.5% as of May 31, 2026; engineering 99.0%, procurement 99.3%, construction 91.4% complete.
- Commissioning of Line 1 is targeted to begin in July/August 2026.
- Mesabi Metallics reports the project is fully financed to first production, a claim TMCR has not independently verified.
- TMCR holds a royalty interest in the project and does not operate or control it.